April 26th, 2000

The electrical wiring, the plumbing and most of the A/C ductwork is completed. We had our septic system installed and found out that the grade for the septic system "hill" will meet right up to a portion of the porch. Cindy and I actually like the idea of walking off the porch without needing stairs.

The Great room windows were delivered and will be installed this week. Work has begun on wall coverings on areas that will not require an inspection. Once the inspections are completed, the wall coverings will move real quick. The stair landing has been built and the stairs should be done within the next two weeks. Once the framing and roofing inspection passes, they will install the roofing shingles.

Things are progressing well. We had a delay due to the A/C people, but we are coping with it.

Thanks for being part of our dream.